Stage 1 – Progress report

Progress report.

Buces Cutting to Mendlesham Ford.

This section of the line has been walked and the original trackbed has been recorded on its southern alignment running parallel with Brockford Road and east parallel with Buces Lane.
Most of the trackbed is intact apart from rabbit damage and a section where recent drainage work has resulted in the unfortunate destruction of a small section of the track bed.
We have yet to clearly establish the owner and / or tenant is who farms this land and if the owner would be willing to sell / lease the area the trackbed sits on. This is currently in hand and should be resolved by September 2015. (08/2015 RF)